Daytime Closures at Hampshire Road Wednesday, July 16 through Friday, July 18

Northbound US 101 On-Ramp at Hampshire Road Closed Wednesday Night, July 9 

The Hampshire Road on-ramp to the northbound US 101 freeway will be closed from 8 p.m. Wednesday, July 9 to 6 a.m. Thursday, July 10. This closure will allow the contractor to complete a concrete pour on a retaining wall that is being constructed along the ramp. Intermittent nighttime closures of this ramp will continue over the next few weeks. 

Daytime Road Closures at Hampshire Road Beginning Wednesday, July 16

As part of the US 101 bridge widening at Hampshire Road, preparations are under way to begin pile driving the week of July 14. Pile driving is a common method of constructing bridge foundations. To support the bridge foundation, steel or concrete beams (known as "piles") are driven into the ground by a large hammer mounted atop a crane, until the beams reach a hard layer of earth beneath the foundation. Please be advised, this work may be loud and disruptive due to vibration and pounding.

WHEN/WHERE: In order for the contractor to set up the pile driving crane and other equipment, Hampshire Road underneath the US 101 freeway as well as the northbound US 101 Hampshire Road on- and off-ramps will be closed, from 9 p.m. Monday, July 14 to 6 a.m. on Tuesday, July 15.

Pile driving on Hampshire Road will begin during the day on Wednesday, July 16. Hampshire Road will be closed to through traffic at the US 101 freeway, daily between 9 a.m. and 4 p.m., Wednesday, July 16 through Friday, July 18. The US 101 freeway on- and off-ramps on Hampshire Road will remain open, however there will be no access on the roadway underneath the freeway. To avoid delays, motorists are encouraged to avoid the area and consider using alternate routes.

For more information regarding upcoming closures scheduled on the project, visit www.toaks.org/10123.

DISCLAIMER: Please be advised, dates and times are subject to change due to unforeseen operational factors or inclement weather. Source: 101/23 Project Team.